Burnt Mill Creek
Description:

  • Phase1. Line 720 lf of the existing 48" sewer pipe.
  • Phase 1A. Rehabilitate or replace junction boxes, manholes and correct undermined pipe supports.
  • Phase 2. Rehabilitate or replace the remaining 2500 lf of 48" pipe and manholes.

 Schedule:

  • Phase 1 - Completed
  • Phase 1A - Substantially complete.  Remaining items began construction in late 2009 
  • Phase 2 - In progress.  Construction to begin by end of 2010.

Burnt Mill copy.jpg

The Burnt Mill Creek Outfall serves the Authority's largest sewer shed, collecting flow from several major tributary sewer outfalls and discharges to one of the Authority's largest sanitary sewer pumping stations, Pump Station 10.  This project will include repair, rehabilitation and/or the replacement of approximately 2,600 linear feet of existing 48-inch sanitary sewer outfall along Burnt Mill Creek, from Pump Station Number 10.   Approximately 16 sewer manholes and the headworks structure at Pump Station 10 are included in the anticipated improvements.  Preliminary investigations of the Burnt Mill Creek Outfall area indicate the pipeline and manholes are in critical need of rehabilitation and/or replacement with some difficult working conditions due to wet soils and marsh conditions.  CDM has been approved by the CFPUA Board to design and administer construction for the rehabilitation and/or replacement.  Construction is estimated to cost $2.7 million. 


 



Payment Center & Administrative Offices: 235 Government Center Drive Wilmington, NC 28403
Customer Service: (910) 332-6550 Fax: (910) 332-6352 General (910)799-6064 Fax: (910) 799-6066
Payment Center: 305 Chestnut Street Wilmington, NC
home Home   |   email page Email Page   |   print page Print Page   |   rss feed RSS Feed   |   Site Map   |   Accessibility   |   Copyright Notices   |   Powered by CivicPlus